Natural Resource Assessment

Getting Started
It is important to understand the natural resource requirements of your property at the earliest possible stage of the building process. Our Natural Resource Assessment Process (PDF) aims to provide that information with as much detail and accuracy so that future building permits may be issued as quickly as possible.

This will determine what reviews are necessary regarding:
  • Critical Areas
  • Watershed Regulations
  • Flood Regulations
What to Expect
The Natural Resource (NR) Assessment process works like this:
  • The applicant contacts county NR staff by phone, email, or in person.
  • County NR staff provides a brief review based on the information at hand. At this time, NR staff will determine which NR reviews need to occur. If no NR reviews are required, the NR Assessment may be waived by staff.
  • Return this Submittal Checklist (PDF) and a conceptual development site plan to Whatcom County. NR Staff will take in these documents and determine if staff needs to perform a site inspection to verify critical areas on site.
  • NR Staff may perform a site inspection.
  • NR Staff will then compile a document which outlines all NR requirements of building permit submittal or any issues that may affect future development. If there aren’t any issues or requirements, a NR approval document will be created for submittal with the building permit.
    • If there is information or documentation required prior to building permit submittal, you may submit that information prior to submittal of the building permit. This will allow staff to review and possibly provide a NR approval document, which would lead to minimal NR review of the building permit and potential building permit issuance over the counter.
  • Submittal of a building permit with NR approval or NR requirement document and all documents/studies that are required.
Note
If a proposal is within shoreline jurisdiction you will need to contact a shoreline administrator to obtain the necessary shoreline approval(s). Whatcom County Planning and Development Services will not accept a building permit application without a copy of a shoreline decision for the proposal.