Crisis Stabilization Facility Expansion

WC Triage-1

Update on the Crisis Stabilization Facility:
As of Feb. 20, 2020 we are currently on schedule, all of the high roof trusses have been installed and plywood sheeting is proceeding.
Installation of roof drain piping and plumbing is currently ongoing. The center core of the project is still open as we are waiting for modifications to steel columns; we can then install the lower roof framing, then the walls. 